This year, Christmas Day falls on a Friday, with the Boxing Day bank holiday moved to Monday 28 December and New Year’s Day on Friday 1 January. For a lot of businesses, that means the office sits empty from Christmas Eve until Monday 4 January.
That is around ten clear days with no staff, no meetings and no one to work around. For the right kind of project, it is the best window of the year to get work done without disrupting the business.
The catch is that almost all the planning has to happen before anyone leaves for the holidays. If you are considering it for this year, the time to decide is now.
What Realistically Fits Into the Shutdown
Ten days is enough for a lot, but not for everything. The works that suit the window are ones that are noisy, messy or disruptive, yet fairly contained in scope.
Works that suit the window
- Carpet and floor finish replacement across open-plan areas
- Redecoration, including feature walls and branding
- LED lighting upgrades within existing ceiling grids
- Small office partitioning changes, such as adding a meeting room or splitting a large office
- Acoustic panels and ceiling treatments
- Furniture replacement and reconfiguration
- Data cabling and power repositioning for new desk layouts
Many of these can be combined. A floor, lighting and decoration refresh across 5,000 sq ft is often achievable in the window with the right preparation.
Works that don’t
A full office refurbishment, anything involving significant mechanical and electrical changes, or work needing major structural or landlord sign-offs rarely fits into ten days.
The shutdown can still help with bigger projects, though. Use it for the most disruptive phase, such as strip-out or flooring, and run the quieter stages either side.
Planning Backwards From the Last Working Day
The works themselves are the easy part. What decides whether a shutdown project succeeds is everything that happens in the weeks before.
Six to eight weeks before
Confirm the scope and get a fixed quote. Carpet tiles, glazed partitions, light fittings and furniture can all carry lead times of four to eight weeks, so materials need ordering early.
If you lease the space, check whether the works need landlord approval or a licence for alterations. This step catches people out more than any other.
Three to four weeks before
Agree access with the building manager. Many multi-let buildings reduce security, reception cover and heating over Christmas, and some close entirely for a few days.
Confirm fire alarm arrangements, loading bay slots and any permits needed for out-of-hours work.
The final week
Staff clear desks and personal items. IT backs up and disconnects equipment. Name one decision-maker who will be reachable during the break, because questions always come up on site.
Costs and Practical Considerations
Working over Christmas usually costs more than the same job in February. Bank holiday labour rates, out-of-hours supervision and the need for larger crews to hit a fixed deadline all add up.
What you save is harder to see on a quote but just as real: no lost working days, no temporary relocations and no staff working around dust and noise. For most businesses, that trade-off makes sense.
A few practical points are worth settling early:
- Health and safety duties still apply. Under CDM 2015, the client has legal responsibilities on any construction project, including short ones. Your contractor should provide a construction phase plan.
- Supplier shutdowns matter. Wholesalers and manufacturers close too. Anything not on site by mid-December may not arrive until January.
- Build in snagging time. Aim to finish a day or two before staff return, so issues get fixed before anyone sits down.
Common Mistakes to Avoid
Deciding in December. By then, lead times have usually ruled out most of the options. A shutdown project needs a decision by early to mid November.
Overloading the programme. Squeezing in one extra phase “while the office is empty” is how deadlines slip. A finished smaller scope beats a half-finished larger one on the first Monday back.
Forgetting IT. New layouts mean desks, screens and network points in new places. If IT is not involved from the start, staff return to a fresh office where nothing connects.
Assuming the building is open. Check access dates, heating and lift availability with the landlord or managing agent in writing.
The Takeaway
The Christmas shutdown is a genuine opportunity to improve your workspace without losing a working day. It works when the scope is realistic, materials are ordered early and building access is agreed well in advance.
If you are wondering what could be done in your office over the break, or whether it is still possible this year, speak to the team at SJP Interiors. We can give you a straight answer and a clear plan.